Quick answer

The short version

LOLER 1998 (the Lifting Operations and Lifting Equipment Regulations) covers any lifting equipment used at work, from tower cranes down to slings and shackles. It requires equipment to be strong enough for the job, marked with its safe working load, used under a proper lifting plan, and thoroughly examined by a competent person on a set schedule, 6 months for equipment that lifts people plus all lifting accessories, 12 months for most other lifting equipment.

In short

Key takeaways

  • LOLER applies to almost anything used to lift a load at work, including chains, slings, and shackles, not just cranes.
  • Equipment must be marked with its safe working load and positioned to keep the risk of it failing as low as possible.
  • Thorough examination is a legal requirement, not a nice-to-have, and the interval depends on what the equipment does.
  • A competent person carrying out the examination needs to be independent enough to give an honest verdict, which usually means a third party.
  • Every thorough examination needs a written report, and you need to be able to produce it if an inspector asks.

What Is LOLER 1998?

LOLER stands for the Lifting Operations and Lifting Equipment Regulations 1998 (SI 1998/2307). It's the regulation that sits underneath the Health and Safety at Work Act and deals specifically with lifting kit, how it's inspected, how it's used, and who's allowed to sign off on it.

If your work involves getting a load off the ground, whether that's a hoist lifting a skip of bricks, a crane placing a roof truss, or a chain block pulling an engine out of a plant machine, LOLER is the regulation that applies. It doesn't matter how big or small the lift is. A gin wheel on a scaffold and a 100-tonne mobile crane are both covered by the same set of duties, just with different practical requirements attached.

The regulations were written because lifting failures tend to be sudden and severe. A sling that's been overloaded or a hoist that's never been checked doesn't usually give you a warning before it fails. LOLER exists to catch that risk before it turns into an incident.

Definition

LOLER 1998

The Lifting Operations and Lifting Equipment Regulations 1998 place legal duties on employers and those in control of lifting equipment to make sure it's strong enough, stable, properly marked, used under a planned and supervised lifting operation, and thoroughly examined at set intervals by a competent person.

What Equipment Does LOLER Cover?

LOLER covers lifting equipment and lifting accessories used at work. That's a wider net than most people expect. It includes the obvious big kit and the small bits of gear that get chucked in the back of a van without much thought.

Checklist

  • Tower cranes and mobile cranes
  • Excavators and telehandlers when used to lift a suspended load
  • Mobile elevating work platforms (MEWPs) and scissor lifts
  • Hoists, including builders' hoists and passenger hoists
  • Slings, chains, and wire ropes
  • Shackles and other rigging hardware
  • Chain blocks and lever hoists
  • Gin wheels used for hauling materials up scaffolds
  • Eye bolts and other lifting points fitted to loads
  • Lifting beams and spreader bars
  • Forklifts, when used to raise, lower, or support a load
  • Rope access and abseiling equipment used to support a person

The key test is simple: if it's used to raise or lower a load, or to support a load in a raised position, it's lifting equipment under LOLER. Accessories for lifting, the slings, shackles, and chains that connect the load to the machine, get their own attention in the regulations because they're the parts most likely to be misused, overloaded, or swapped between jobs without a second thought.

What LOLER Requires You to Do

LOLER breaks down into a handful of core duties. Regulation 5 says lifting equipment has to be strong enough and stable enough for the job, and positioned or installed to keep the risk of it striking someone or the load falling as low as reasonably possible. Regulation 6 adds extra precautions where the equipment is being used to lift people, since a fall from a MEWP basket or a passenger hoist is a different order of risk to a dropped pallet. Regulation 7 requires equipment to be marked with its safe working load (SWL), so anyone using it can see at a glance what it's rated for. Regulation 8 says lifting operations involving lifting equipment must be properly planned, supervised, and carried out by people who are competent to do it. Regulation 9 sets out the thorough examination requirements, which is where most of the day-to-day compliance work actually sits.

In practice, this turns into a routine you build into how the job runs, not a one-off form you fill in and forget.

Step by step

  1. 1
    IdentifyList every piece of lifting equipment and every accessory being used on the job, from the crane down to the shackles.
  2. 2
    AssessCheck the load, the ground conditions, and the swept path, and work out whether the equipment is rated and suitable for what you're about to lift.
  3. 3
    PlanPut together a lifting plan that sets out how the lift will be carried out safely, who's doing what, and what happens if something changes.
  4. 4
    ExamineConfirm every item has a current thorough examination certificate before it goes anywhere near the job, and arrange one if it doesn't.
  5. 5
    RecordKeep the thorough examination reports and lifting plan on file and make them available if an inspector asks.
  6. 6
    MaintainTake equipment out of service straight away if a defect is found, and don't let it back on site until it's been fixed and re-examined.

A lifting plan doesn't need to be a huge document for a straightforward lift. For a simple job it might be a page covering the load weight, the equipment being used, who's supervising, and the exclusion zone. For a complex lift, like a crane working near overhead lines or lifting over an occupied building, it needs a lot more detail and sign-off from someone competent to plan lifts of that type.

Thorough Examination: When and How Often

Thorough examination is the part of LOLER that trips people up most, mainly because the interval isn't the same for everything. The regulations set two main intervals, and getting them mixed up is an easy way to end up with expired paperwork on site.

Thorough Examination Intervals

Thorough Examination Intervals
Equipment TypeIntervalExamples
Equipment used to lift peopleEvery 6 monthsPassenger hoists, MEWPs, abseiling and rope access gear
Lifting accessoriesEvery 6 monthsSlings, chains, shackles, eye bolts, lifting beams
Other lifting equipmentEvery 12 monthsCranes, forklifts used for lifting, hoists not used to lift people, chain blocks

On top of the routine schedule, a thorough examination is also needed before equipment is used for the first time, after it's been installed or assembled on a new site, and after any exceptional circumstance that could have affected its safety, things like a near miss, an overload, damage from an impact, or a long period out of use. If in doubt, the safer move is to get it checked rather than assume it's fine.

Don't confuse a thorough examination with routine maintenance or a pre-use check. A pre-use check is something the operator does before each shift, looking for obvious damage or wear. A thorough examination is a formal inspection carried out by a competent person, and it results in a written report, not just a tick on a checklist.

Who Can Carry Out a Thorough Examination?

LOLER says the thorough examination has to be done by a "competent person," and that phrase carries more weight than it sounds. It doesn't just mean someone who's used the equipment before. It means someone with the right training, knowledge, and practical experience to spot defects, and who is independent enough from the work to give an honest report even if that means condemning equipment that's due to be used the next day.

For most small and medium contractors, that independence requirement means bringing in a third-party inspection body rather than getting a member of staff to sign off their own kit. Some larger organisations have in-house engineers who are genuinely independent of the operational pressure to keep equipment running, but for most trades on site, a third-party competent person is the practical route.

The HSE's Approved Code of Practice, L113 (Safe Use of Lifting Equipment), sets out what's expected of a competent person and how thorough examinations should be carried out. It's worth reading if you want the detail behind the regulation rather than just the summary version.

Once the examination is done, Regulation 9(3) requires the report to be kept and made available if an inspector asks for it. Losing the paperwork is treated much the same as not having done the examination at all, so keep copies somewhere you can actually find them, not just in a folder on a site cabin desk that gets cleared out at the end of the job.

LOLER vs PUWER: What's the Difference?

LOLER and PUWER get mentioned in the same breath a lot, and they do overlap, but they're not the same thing. PUWER (the Provision and Use of Work Equipment Regulations) covers work equipment in general, everything from a drill to an excavator, and deals with things like guarding, maintenance, and making sure operators are trained. LOLER is narrower and deals specifically with the lifting side of things.

Comparison

Comparison
LOLER 1998PUWER 1998
Covers equipment used to lift or lower loadsCovers all work equipment, lifting or not
Requires marking with safe working loadNo SWL marking requirement
Requires thorough examination on a set schedule (6 or 12 months)Requires inspection appropriate to the equipment and its use, not a fixed schedule
Focuses on lifting plans, supervision, and competent examinationFocuses on suitability, guarding, maintenance, and operator training
Applies to slings, chains, and other lifting accessories specificallyDoesn't single out lifting accessories as a separate category

A telehandler is a good example of where both apply at once. PUWER covers it as a piece of work equipment, so it needs to be maintained, guarded where necessary, and operated by someone trained on it. The moment that telehandler is used to lift a suspended load with a jib and hook rather than forks, LOLER kicks in as well, and the thorough examination and lifting plan requirements come into play. Most bits of construction plant with a lifting function are dealt with under both regulations at the same time, not one or the other.

Common Mistakes

Common mistakes

  • Treating slings and shackles as disposable consumables that don't need their own examination record.
  • Assuming a 12-month interval applies to everything, when accessories and people-lifting equipment need checking every 6 months.
  • Letting equipment go back into use after a defect is found without a re-examination confirming it's fixed.
  • Relying on a verbal 'it's fine' from whoever owns the crane instead of asking to see the current thorough examination certificate.
  • Writing a lifting plan once and reusing it for a different lift without checking the load, ground, or exclusion zone still match.
  • Losing thorough examination reports instead of keeping them somewhere they can be found if an inspector asks.
  • Confusing a daily pre-use check with a thorough examination, they are not the same thing and don't replace each other.

Frequently asked questions

Does LOLER apply to small lifting jobs, like a chain block in a workshop?

Yes. LOLER applies to lifting equipment used at work regardless of size or how often it's used. A chain block, a gin wheel on a scaffold, or a set of slings in a van all need to be marked with their safe working load and thoroughly examined on the same schedule as bigger kit. The scale of the equipment doesn't change the legal duty.

What happens if a thorough examination finds a defect?

The competent person will note the defect on the report and say whether it's an immediate danger or something that needs fixing within a set timeframe. If it's an immediate danger, the equipment has to come out of use straight away and can't go back into service until it's been repaired and re-examined. Ignoring a defect report and carrying on using the equipment is exactly the kind of thing an HSE inspector will pick up on.

Can I do my own thorough examination if I'm experienced with the equipment?

Not usually. Being experienced with using equipment isn't the same as being a competent person for the purposes of a thorough examination. LOLER expects the examiner to have relevant training and knowledge and to be independent enough from the operational pressures of the job to give an honest assessment. For most contractors, that means using a third-party inspection body rather than checking your own kit.

Do hired lifting equipment and accessories still need checking?

Yes. Hired equipment should come with a current thorough examination certificate from the hire company, but it's still worth checking the certificate is in date and covers the specific item you've been given, not just the fleet in general. If you supply your own slings or shackles to use with hired plant, those need their own valid examination too.

How does LOLER connect to my risk assessment and RAMS?

Lifting operations should show up in your risk assessment as a specific hazard, with the controls referencing the lifting plan, the competent person's sign-off, and the current examination status of the equipment. If the lift also involves working near an edge or at height, it needs to line up with your approach under the Working at Height Regulations too, since the two often overlap on site.

Important safety warning

Using lifting equipment that's overdue a thorough examination, or carrying on after a defect has been flagged, isn't just a paperwork breach. It's the kind of gap that shows up right before a serious failure, a dropped load, a collapsed hoist, a snapped sling. HSE inspectors treat missing or expired LOLER paperwork as a red flag and will act on it, including issuing improvement or prohibition notices that stop work on the spot.

Next step

Get your RAMS sorted

Getting your lifting operations right on paper is a big part of getting them right on site. RAMS Builder helps you put together clear, trade-specific RAMS that cover lifting equipment, competent person checks, and the rest of your site controls, without wrestling with a Word template from scratch.

Build your construction RAMS
LOLER 1998: Lifting Operations Guide for Construction | RAMS Builder Blog | RAMS Builder