Start with strip-out and demolition hazards, then tailor the sequence, surveys, exclusion zones, dust controls and plant arrangements to the structure and live site.

HSE-aligned hazardsSite-ready PDF exportDigital sign-off
Demolition Operative example RAMS
Loading PDF
Rendering document
100%

What's included

Everything you need to prepare a practical demolition operative RAMS.

  • Manual and mechanical demolition hazard examples
  • Prompts for surveys, debris, dust and plant controls
  • 5×5 risk matrix with pre- and post-control ratings
  • Professional PDF export with your branding
  • Digital sign-off and audit trail

Common demolition operative jobs

RAMS Builder includes guided examples for these typical demolition operative tasks.

Soft strip and internal demolitionManual demolition with hand toolsMechanical demolitionConcrete breakingSite clearance and segregationDemolition waste handling

Typical hazards and controls

Pre-loaded hazards and controls for demolition operative work.

Unexpected structural movement or collapse

  • Review relevant surveys and demolition sequence
  • Set exclusion zones
  • Stop work and escalate if conditions differ from the plan

Falling debris and flying fragments

  • Control the drop zone
  • Use suitable screens or suppression
  • Keep people clear of the demolition area

Dust, including potentially hazardous materials

  • Confirm survey information before intrusive work
  • Use suppression and suitable containment
  • Select RPE from the site-specific assessment

Plant, tool and pedestrian interface

  • Segregate pedestrians and plant
  • Use a trained signaller where required
  • Agree controlled routes and communication

Method statement steps

A typical method sequence for demolition operative work.

  1. 1Review the scope, surveys, services information and demolition sequence
  2. 2Isolate or verify services and establish controlled access
  3. 3Set barriers, exclusion zones, welfare and dust-control measures
  4. 4Carry out strip-out or demolition in the agreed sequence
  5. 5Remove and segregate waste without overloading the work area
  6. 6Inspect the area, leave it stable and hand over to the site team

Example output

Review a fully featured demolition operative RAMS example with hazards, permits, COSHH, and sign-off details.

Demolition Operative example RAMS PDF

See how the finished document is structured before you customise it for the live site.

Frequently asked questions

Common questions about demolition operative RAMS.

What should be checked before intrusive demolition starts?

Confirm the scope, available structural and asbestos information, services status, access, neighbouring occupiers, emergency arrangements and the sequence approved for the actual structure.

How should asbestos risk be addressed in demolition RAMS?

Reference the relevant survey information and make clear that suspect materials must not be disturbed. Stop work and follow the site escalation process if materials differ from the information available.

How do I control dust and debris?

Plan suppression, containment, controlled drop zones, waste routes, housekeeping and appropriate PPE or RPE. Adapt these controls to the material, method and people who could be affected.

Build your document

Ready to create your demolition operative RAMS?

Start from the example, customise it for the live job, and export a site-ready PDF when you're happy.

Create RAMS for your work

Sign up to create a RAMS document for your project with the details that apply to your work.